Eaton Socon
UnknownNGETNGET400 kV
Site Summary
Voltage Levels
1
Best Gen RAG
unknown
Best Gen Headroom
N/A
Best Demand Headroom
N/A
Operators
NGET
Generation Connection Queue
Embedded Capacity Register + NESO TEC2.3 GW
Queued
0.0 MW
Connected
4
Projects
| Project | Technology | Capacity | Status |
|---|---|---|---|
| Eaton Socon High Impact Green Energy Hub (HIGEH) 1 | Energy Storage System;Nuclear;PV Array (Photo Voltaic/solar);Reactive Compensation;Wind Onshore | 1000.0 MW | Scoping |
| Little Barford | CCGT (Combined Cycle Gas Turbine);Energy Storage System | 740.0 MW | Built |
| Eaton Socon Solar | Energy Storage System;PV Array (Photo Voltaic/solar) | 500.0 MW | Scoping |
| Eaton Socon PV Storage | Energy Storage System;PV Array (Photo Voltaic/solar) | 49.9 MW | Scoping |
Voltage Levels (1)
Data Source
Primary DNO:NGET
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.